It takes 18 electricians 35 days to wire a new housing subdivision. How many days would 28 electricians require to do the same job?

Answers

Answered by Ms. Sue
18/35 - 28/x

Cross multiply and solve for x.

Answered by allie
I got 54.(4)

but my teacher says its wrong
Answered by Ms. Sue
Sorry. My brain took a brief break. This is not a viable proportion.



Answered by allie
I got 14
and it wrong
Answered by Stevium
dis is inverse proportion: let w be no of days,find constant k : 18=K/35,K=630, 28=630/w,find your w
Answered by Damon
one electrician would take
18 * 35 = 630 days
so
28 electricians would take
630/28 = 22.5 days
Answered by Sam
@ Ms. Sue, you simply cannot cross multiply because it is an inverse proportion, rather it would be 630 (total days) divided by total workers (28) equaling 22.5 days. @Damon, you are right!
Answered by Dude
Here is the simple way:
First divide 35 by 28 which is 1.25.
Then, multiply 1.25 and 18 together.
22.5 is your answer.
Answered by Max
22.5 days
Answered by lol
thanks for the work
Answered by V.C
22.5