It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians require to do the same job?

Answers

Answered by PsyDAG
24/15 = x/18

Solve for x.
Answered by Anonymous
x=28.8
Answered by Anonymous
28.8/18=1.6
Answered by Anonymous
it takes them 20 days
Answered by Anonymous
Wow way to show your work
Answered by Grego
15/18 = .8333333(infinite)

15/18 x 24 = 20

(Yes I was the person complaining about lack of work)
Answered by allie
and i was the one who did not show the work
Answered by Anonymous
It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians take to do the same job, assuming all electricians work at the same pace?