A can do a piece of work in 12 days whereas B can destroy the work in 3 days. A does the work for 10 days and then B destroys the work up to 2 days. In how many days will the work be finished?
9 years ago

Answers

MathMate
Fraction of work accomplished W at the end of day t will be denoted W(t).
W(0)=0
W(10)=5/6
W(12)=5/6-2/3=1/6
W(22)=1/6+5/6=1 work completed.
9 years ago

Related Questions

P can do a piece of work in 9 days. Q is 50% more efficient than P. The number of days it takes Q t... 3. A can do a piece of work in 6 days. B is 50% more efficient. The number of days it take B to do w... 20 men can do a piece of work in 24 days. After working for 6 days, an additional number of men are... A and B can do a piece of work in 12 days. They started to work together but A left after a few days... A and B can do a piece of work in 10 days, B and C in 15 days, A and C in 12 days. A,B and C work to... A and B can do a piece of work in 10 days, B and C in 15 days and A and C in 12 days. A,B and C wor... 9 men do a piece of work in 28 days. How many men will do it in 56 days? What a piece of work is a man! How noble in reason, how infinite in faculty! In form and moving how... What a piece of work is a man! How noble in reason, how infinite in faculty! In form and moving how...
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use