20 men can do a piece of work in 24 days. After working for 6 days, additional men are employed to finish the work in 21 days from the beginning. Find the number of additional men
10 years ago

Answers

Steve
each man can do 1/(20*24) = 1/480 of the job in a day.

So, in 6 days, they have done 6*20/480 = 1/4 of the work.

So, if the new men work at the same speed, you need to do 3/4 of the job in 15 days.

m additional men can do 15m/480 = m/32 of the job in 15 days. So, we need

m/32 = 3/4
m = 24
10 years ago

Related Questions

P can do a piece of work in 9 days. Q is 50% more efficient than P. The number of days it takes Q t... 3. A can do a piece of work in 6 days. B is 50% more efficient. The number of days it take B to do w... 20 men can do a piece of work in 24 days. After working for 6 days, an additional number of men are... A and B can do a piece of work in 12 days. They started to work together but A left after a few days... 32 men can do a piece of work in 18 days. In how many days will 72 men do it? For 30 buffaloes, t... A and B can do a piece of work in 10 days, B and C in 15 days, A and C in 12 days. A,B and C work to... A can do a piece of work in 12 days whereas B can destroy the work in 3 days. A does the work for 10... A and B can do a piece of work in 10 days, B and C in 15 days and A and C in 12 days. A,B and C wor... 9 men do a piece of work in 28days (a). How long will it take 14 men to do it? (b). how many men...
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use