20 men can do a piece of work in 24 days. After working for 6 days, an additional number of men are taken to finish the work in 21 days from the beginning. Find the number of additional men .
.
.
I tried using variation method but the answer didn't come correct :(
.
.
I tried using variation method but the answer didn't come correct :(
Answers
Answered by
Steve
in 6 days, the 20 men have done 1/4 of the work.
One man can do 1/480 of the work in a day.
So, if x men finish 3/4 of the work in 15 more days, that means
x/480 * 15 = 3/4
x = 24
So, 4 extra men were hired.
One man can do 1/480 of the work in a day.
So, if x men finish 3/4 of the work in 15 more days, that means
x/480 * 15 = 3/4
x = 24
So, 4 extra men were hired.
Answered by
mark
thank you very much sirr.
Answered by
mark
But I didn't get what the question says. 21 days from the beginning..... ??
Answered by
Prashant Sindhuliya
In 1 day 20 men can do 1/24 of work, In 6 days 20 men can do 1/24*6=1/4 work, Remaining work=1-1/4=3/4 work, Let x denoted added men, Remaining work is completed by 20+x men in (21-6=15) days, 20 men can do 1 work in 24 days.........(i) 20+x men can do 1 work in 15*4/3= 20 days.......(ii) Sloving equation i and ii, we get, x=4 days
Answered by
Lucky
Gaurav and saurav can do a peice of work in 20 days and saurav can do it in 30 days. They start to together but gaurav left after 4 days.In how many days would saurav finish the remaining work
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.