40 MEN CAN DO A PIECE OF WORK IN 30 DAYS,WORKING 8 HOURS DAILY.IN HOW MANY DAYS WILL 60 MEN FINISH THE WORK WHEN WORKING HOURS ARE REDUCED BY 25 PERCENT? A,19 B,30 C 20 1/3 D,26 2/3

Answers

Answered by Steve
40 men @ 8 hrs/day = 320 man-hrs/day
60 men @ 6 hrs/day = 360 man-hrs/day

So, it will take 320/360 = 8/9 as long, or 80/3 days