3. A can do a piece of work in 6 days. B is 50% more efficient. The number of days it take B to do work is
A. 9
B. 3
C. 2
D. 4
Is the answer 4? If so, how did you get your answer?
A. 9
B. 3
C. 2
D. 4
Is the answer 4? If so, how did you get your answer?
Answers
Answered by
Steve
3/2 as productive means it takes 2/3 as much time. So, (D).
Answered by
7th grade Math
What do you mean?
Answered by
Steve
Looks like you need to study what <u>50% more efficient</u> means. It means B can do 50% more work than A in a given time.
50% = 0.5
So, 50% more means 1.5 times as much. That's 3/2.
Think about it. If I do twice as much as you, it takes half (1/2) as long.
If I do 3/2 as much as you, it takes 1 /(3/2) = 2/3 as long.
50% = 0.5
So, 50% more means 1.5 times as much. That's 3/2.
Think about it. If I do twice as much as you, it takes half (1/2) as long.
If I do 3/2 as much as you, it takes 1 /(3/2) = 2/3 as long.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.