If it takes 4 people 20 days to build a house, how long does it take 6 people. I know the answer is 15 days, but for the life of me I can't figure out the formula for it.
16 years ago

Answers

MathMate
20 days are required for 4 people to build a house. So it takes 4*20=80 man-days.
If we have 6 people, then it <i>should</i> take 80/6=13.3 days to finish the house.
16 years ago

Related Questions

Suppose it takes 3 days for a space vehicle to travel from earth to the moon. How long for the same... Suppose it takes 3 days for a space vehicle to travel from the earth to the moon. About how long wou... If it takes 45 days for 80.0 mg of a particular radioactive isotope to decay to 10.0 mg what is its... The earth takes 365 1/4 days to go around the sun. Mercury takes 3 days less than 1/4 of this time.... If it takes 10 people 6 days to do a home improvement, how long would 4 take It takes 5 people 3 days to put up a fence? How many days would 3 people take? if it takes 5 men 7 days to dig a hole, how long will it takes 3 men to dig half a hole? If a worker takes 4 days to paint a house and another worker takes 8 days to paint the same house. H... It takes 30 days when 8 men construct a flat. How many men is needed to construct the same flat in... It takes 29.5 days for the Moon to orbit Earth. How many days and hours does it take for the Moon...
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use