Asked by Magic
if it takes 5 men 7 days to dig a hole, how long will it takes 3 men to dig half a hole?
Answers
Answered by
oobleck
3/5 as many men, so 5/3 as long for one hole.
That is, it will take 3 men 7 * 5/3 = 35/3 days to dig a whole hole.
so how long for 1/2 a hole?
That is, it will take 3 men 7 * 5/3 = 35/3 days to dig a whole hole.
so how long for 1/2 a hole?
Answered by
R_scott
7 * 5 = 35 ... man-days to dig hole
half a hole takes 35/2 man-days
(35/2) / 3 = 35/6 man-days for half a hole ... almost six days
half a hole takes 35/2 man-days
(35/2) / 3 = 35/6 man-days for half a hole ... almost six days