If it takes 10 people 6 days to do a home improvement, how long would 4 take
9 years ago

Answers

Damon
60 person days/job

(1/60) job/person day

(1/60)job/person day *(4) persons = 4/60 job/day = 1/15 job/day
so
15 days
9 years ago
Steve
4/10 as many people means 10/4 as long to work.

5/2 * 6 = 15
9 years ago

Related Questions

Suppose it takes 3 days for a space vehicle to travel from Earth to the moon. About how long would i... If it takes 4 people 20 days to build a house, how long does it take 6 people. I know the answer is... It takes 4 workers five days to clean 180 miles of highway. How many workers are needed to clean 250... it takes 7 men 10 days to build a garage.Halfway through building the garage they get some help from... It takes 3 artists 24 days to paint a building. Calculate how long it will take 6 artists to paint t... If it takes 45 days for 80.0 mg of a particular radioactive isotope to decay to 10.0 mg what is its... It takes 5 people 3 days to put up a fence? How many days would 3 people take? if it takes 5 men 7 days to dig a hole, how long will it takes 3 men to dig half a hole? It takes 30 days when 8 men construct a flat. How many men is needed to construct the same flat in... It takes 29.5 days for the Moon to orbit Earth. How many days and hours does it take for the Moon...
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use