The volume is pi D^2/4 * H
In cubic ft, this is
(3.14)*(1/4)*(4)^2*(16)= 201.0 ft^3. Divide by 27 ft^3/yard^3 for the number of cubic yards.
Then multipy by $75/yard^3 for the cost.
How many cubic yards of concrete will it take to fill a cylindrical column that is 16 feet high and whose diameter is 4 feet?
Use pi=3.14
(round your answer to the nearest TENTH)
If a cubic yard of concrete costs $75, using the rounded answer from above, what would be the cost for the concrete (rounded to the nearest dollar)
3 answers
would it be 7.4 cubic yards
and 558 dollars
and 558 dollars
Yes.