. A 475 kg pre-stressed concrete beam is to be raised 10.0 m in 24.0 s. How many kilowatts of power
is needed for the job?
10 years ago

Answers

Answered by Damon
power = work/time

work = weight * distance up
= 475*9.81*10
so
power = 475*9.81*10 / 24 Joules/second or Watts

divide by 1000 for kilowatts
10 years ago
Answered by wellington
1.9415625
10 years ago

Related Questions

How many cubic yards of concrete will it take to fill a cylindrical column that is 16 feet high and... How many cubic yards of concrete will it take to fill a cylindrical column that is 24 feet high and... How many cubic yards of concrete are needed to make 1200 square concrete posts 9 inches by 9 inches... a 0.5KG ball is drop at concrete incline which is 45 degree above the horizontal then bounces off wi... Why do you think that a concrete poem is the best way to communicate? Jordan wants to build a concrete patio that will be 9 yards by 11 yards. It will cost $7.00 per squa... Peter is building a new concrete step up to his back patio. The step will be shaped like a rectangul... The Rose That Grew From Concrete Did you hear about the rose that grew from a crack in the concret... elaborate a perfect and concrete answer to the fallowing with 0 plagiarism score Think about an inst... Does this video contain concrete tips to help kids determine good vs. bad information online? Explai...
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use