The life cycle cost of the BLUEBIRD system is $600 million. The program acquisition cost is $400 million and the development cost is $150 million. There are no facilities costs. What is the procurement cost of the BLUEBIRD system?
$200 million
$150 million
$250 million
$100 million
3 answers
250
Your program has a research and development project scheduled to start in January 2004 which is expected to take 40 months to complete. The project is expected to cost a total of $150 million (then-year dollars), with cost expected to be incurred as follows:
A) FY04 $ 20 million
B) FY05 $ 48 million
C) FY06 $ 50 million
D) FY07 $ 32 million
:
A) FY04 $ 20 million
B) FY05 $ 48 million
C) FY06 $ 50 million
D) FY07 $ 32 million
: