Asked by Anonymous
your acquisition program expects to award a vehicle production contract in April 2005. The first item from this contract is expected to be delivered in January 2006. The estimated unit cost for each vehicle is $1 million (then-year dollars and the contractor can deliver exactly 3 items per month beginning January 2006.