the following rational function gives the number of days it would take two construction crews, working together, to frame a house that crew 1 (working alone)could complete in t days and crew 2 (working alone) could complete in t+3 days. f(t)=(t^2+3t)/(2t+3). (a) if crew 1 could frame a certain house in 24 days, how long would it take both crews working together? (b) if crew 2 could frame a certain house in 32 days, how long would it take both crews working together?
Answers
Answered by
Steve
It's easier to work with
1/f(t) = 1/t + 1/(t+3)
For crew 1, 1/t = 1/24, so t=24
Thus 1/f(t) = 1/24 + 1/27 = 17/216
So, both crews can do it in 216/17 days
For crew 2, 1/(t+3) = 1/32, so t=29
Now 1/f(t) = 1/29 + 1/32 = 61/928
So, both crews can do it in 928/61 days
1/f(t) = 1/t + 1/(t+3)
For crew 1, 1/t = 1/24, so t=24
Thus 1/f(t) = 1/24 + 1/27 = 17/216
So, both crews can do it in 216/17 days
For crew 2, 1/(t+3) = 1/32, so t=29
Now 1/f(t) = 1/29 + 1/32 = 61/928
So, both crews can do it in 928/61 days
Answered by
Dee
Thank you Steve, that was a big help.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.