Question
The following data relate to direct labor costs for the current period:
Standard costs 6,000 hours at $12.00
Actual costs 7,500 hours at $11.60
What is the direct labor rate variance?
Answer
A.$15,000 unfavorable
B.$3,000 favorable
C.$17,400 unfavorable
D.$2,400 favorable
Standard costs 6,000 hours at $12.00
Actual costs 7,500 hours at $11.60
What is the direct labor rate variance?
Answer
A.$15,000 unfavorable
B.$3,000 favorable
C.$17,400 unfavorable
D.$2,400 favorable
Answers
Direct labor rate variance
(AR-SR)AH
(11.6-12)(7500)
= $ 3,000 favorable
The following data relate to direct labor costs for the current period:
standard cost36000hours $22
actual cost 35000hours $23
What is the direct labor time variance?
standard cost36000hours $22
actual cost 35000hours $23
What is the direct labor time variance?
Related Questions
Tusk pty ltd uses standard costs system for its single product in which variable manufacturing overh...
If given the Selling price, the direct labor costs and other variable costs how do you determine the...
The standard costs and actual costs for direct labor for the manufacture of 2,500 actual units of pr...