Suppose a team creates a shared spreadsheet that lists all pending tasks. Each team member picks a task and moves it to a separate worksheet in the file. When that task is completed, its owner moves it to a third worksheet. The team checks in regularly to ensure work is distributed evenly and no task is held up waiting on another. Which methodology is this team using?(1 point)

Responses

scrum
scrum

extreme programming
extreme programming

Kanban
Kanban

waterfall

1 answer

The methodology that this team is using is Kanban. Kanban is characterized by visualizing work, limiting work in progress, and managing flow, which aligns with the team's use of a shared spreadsheet to track tasks across different stages (pending, in progress, completed).