Suppose a team creates a shared spreadsheet that lists all pending tasks. Each team member picks a task and moves it to a separate worksheet in the file. When that task is completed, its owner moves it to a third worksheet. The team checks in regularly to ensure work is distributed evenly and no task is held up waiting on another. Which methodology is this team using?(1 point)

Responses

Kanban
Kanban

scrum
scrum

waterfall
waterfall

extreme programming

1 answer

The methodology that this team is using is Kanban. Kanban is a visual workflow management method that helps teams visualize tasks, track progress, and manage work in progress. The use of a shared spreadsheet with different worksheets for pending tasks, in-progress tasks, and completed tasks aligns well with the principles of Kanban.