If a job takes 64 men to complete in 15 days, how many more men will take to complete the job in 12 days?

1 answer

64*15 = 12n

let n be number of workers

divide both sides by 12

(64*15)/12 = (12n)/12
80 = n

thus it takes 80 men to complete the job in 12 days.