Case Study: Calcutta's Metro

In 1996, Calcutta’s long-waited metro finally opened to a collective sigh of relief from the long-suffering population of this large Indian city. Critics had long derided the project a one of the “slowest-moving” public works projects ever conceived and implemented. The single route line, comprising 17 stations and slightly more tan 10 total miles of track, had taken 23 years from the date it was first approved at a final estimated cost of almost $5 billion. To put this figure into perspective, New York City’s subway system boasts 656 miles of mainline track and 468 stations, all for a city whose population is significantly less than Calcutta’s estimated 11 million residents. Calcutta’s Metro project represents a textbook example of the problems that can arise from poor planning.

The project was initially hampered by poor funding that slowed the development process. However, it was during project planning that a number of constraints became apparent that were to negatively impact on the project. For example, one factor that impeded progress was the decision to begin construction right in the middle of the city. Rather than start at one of the two terminal points, the project managers elected to begin digging in the city center, first tunneling down and then in both directions simultaneously, The problems with soil removal and heavy equipment transportation rose dramatically as a result. Among the other factors that the Metro project had to work around were:

1. Exclusive possession of the site was not possible. Normal life in the city had to go on as usual. While this is a normal by-product of most metropolitan construction, in a city the size and congestion of Calcutta, with an inadequate road system to begin with, there was a constant battle between maintaining normal traffic flows and creating enough buffers to allow for Metro construction.
2. Traffic could not be fully diverted from the roads. The road system was almost completely inadequate to start. It was, therefore, impossible to divert traffic from already dreadfully overcrowded thoroughfares.
3. Uncharted utilities (sewer, water, gas mains, phone, electric cables). By far of the worst features of construction was the near total absence of a master plan showing the location of underground utilities and cable lines? Work was continually started, stopped, and gradually restarted as crews and await their repairs to the infrastructure.
4. Shops around the site had to be provided with view and approach. Local shop owners were justifiably worried about the effect on their commerce of closing off access to their shops while construction went on. They actively worked against Metro development until they were individually provided with access lanes from their shops to the still-operating streets.

Another unforeseen problem resulted from the large bureaucracy that sprang up around the Metro’s construction. Utilizing thousands of laborers, the project organization led to the creation of a huge social umbrella for employees and the families, as housing, schools, and medical centers were created and subsidized by the Metro Authority for the life of the project. In fact, one critic argued that it was wishful thinking to assume that workers would be motivated to quickly complete a project that provided such a comprehensive set of benefits for them and their families.

and answer the following questions:

1. Assume that you are the mayor of Calcutta, soliciting bids for the construction of the Metro. How would you construct a Statement of Work for the project to encourage efficient and creative means for undertaking this project?

2. Which of the problems the Metro project faced were the result of a poorly conceived project scope and how much was due to simple bad luck? Defend your position.

5 answers

Animal, when you have answered these as best you can, please repost and someone here will be happy to give you suggestions and let you know where you need to make corrections.

=)
line, comprising 17 stations and slightly more tan 10 total miles of track, had taken 23 years from the date it was first approved at a final estimated cost of almost $5 billion. To put this figure into perspective, New York City’s subway system boasts 656 miles of mainline track and 468 stations, all for a city whose population is significantly less than Calcutta’s estimated 11 million residents. Calcutta’s Metro project represents a textbook
casual to say the country is getting smaller. Because people are more manageable today and because of their improvements in travel and communication. In the 90’s the metro suffer the largest population of India City, critics had long desired the projects ever and implemented. To Calcutta’s Metro project represents an example of the problems that can arise from poor planning. For example: one of the factors was the decision to begin construction in the heart of the City. Instead starting at one of the termination points.
Normal life in the city had go on as usually product of most metropolitan construction, in a city the size and congestion of Calcutta with an inadequate road system to begin with. Another problem resulted from large bureaucracy that sprang up around the Metro’s construction. Utilizing thousands of labors, the project organization led to the creation of a huge social umbrella for workers and fa
so ran
all the problems are due to poorly conceived project scope
Similar Questions
    1. answers icon 1 answer
  1. 5 of 55 of 5 ItemsQuestion Which word best completes the following sentence? A motorcycle taxi is called a _______ in La
    1. answers icon 1 answer
  2. Order the measurements from smallest (1) to largest (4).* 1 2 3 4 metro kilometro milimetros centimetro metro kilometro
    1. answers icon 1 answer
    1. answers icon 1 answer
more similar questions