Activity Time Predecessor(s)

A 3 None
B 4 A
C 3 B
D 5 B
E 10 C, D
F 3 E
G 6 E
H 5 G, F

Please assist with finding the ES, EF, LS, LF and slack time for ALL activities.
also, the critical path?
and, the project completion time?