. Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path:

Activity Activity Predecessor Time (months)
1 ___ 4
2 ___ 7
3 1 8
4 1 3
5 2 9
6 3 5
7 3 2
8 4,5,6 6
9 2 5
13 years ago

Answers

Related Questions

A Gantt Chart is good for planning but not an effective tool for control. Can you please let me know... I AM MAKING A GANTT CHART IN MS PROJECT.I CANNOT CHANGE THE START AND FINISHVDATE...IT IS SOMEHOW BL... Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a p... A Gantt chart is good for planning but not an effective tool for control. . True False What is tracking Gantt chart FCFS Gantt Chart with Completion Times 9. SJN Gantt Chart with Completion Times Draw a Gantt chart that shows the completion times for each process using first-come, first-served... Draw a Gantt chart that shows the completion times for each process using first-come, first-served... Draw a Gantt chart that shows the completion times for each process using shortest job next CPU sch...
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use