A city spends $15 million on a beach nourishment project that adds 1.8 million cubic yards of sand to 3 miles of beach. What is the cost per cubic yard of sand? (1 point)

Responses

$8.33 per cubic yard
$8.33 per cubic yard

$12.00 per cubic yard
$12.00 per cubic yard

$0.60 per cubic yard
$0.60 per cubic yard

$5.00 per cubic yard

1 answer

To find the cost per cubic yard of sand, you can use the following formula:

\[ \text{Cost per cubic yard} = \frac{\text{Total cost}}{\text{Total cubic yards of sand}} \]

Plugging in the values:

\[ \text{Cost per cubic yard} = \frac{15,000,000 \text{ dollars}}{1,800,000 \text{ cubic yards}} \]

Calculating that:

\[ \text{Cost per cubic yard} = \frac{15,000,000}{1,800,000} = 8.33 \text{ dollars per cubic yard} \]

So the cost per cubic yard of sand is $8.33 per cubic yard.

Similar Questions
    1. answers icon 1 answer
    1. answers icon 1 answer
  1. Date US PopulationJul 1, 2012 313.85 million Jul 1, 2011 311.59 million Jul 1, 2010 309.35 million Jul 1, 2009 306.77 million
    1. answers icon 2 answers
    1. answers icon 1 answer
more similar questions