Your program plans to acquire a total of 600 end items costing $535 million over a five-year period. The first production contract is to be awarded in FY04. The number of items to be procured (not delivered) each year and their estimated cost (in then-year dollars) is shown below:

FY Lot Quantity Total Lot Cost

FY04 50 $ 50 million
FY05 100 $ 95 million
FY06 150 $135 million
FY07 150 $130 million
FY08 150 $125 million

Answers

Answered by PsyDAG
What is your question?
Answered by Anonymous
Assuming there is no advance procurement and that this is NOT a multiyear contract, what is the correct amount to includes in your budget request for FY04 and FY05 for this contract?
Answered by Steve
FY04 50 $50 million
FY05 100 $95 million
Answered by Anonymous
$145 million for FY04 and $ 0 million for FY05
Answered by Karen
$145 million for FY04 and $ 0 million for FY05
Answered by Dude
FY04 50 $50 million
FY05 100 $95 million