In addition to being temporary, which is another characteristic of a project as it is defined by the Project Management Institute (PMI)?

(1 point)
Responses

it is oriented toward an objective

it is oriented toward an objective

it involves getting stakeholder approval

it involves getting stakeholder approval

it includes a kick-off and wrap-up meeting

it includes a kick-off and wrap-up meeting

it requires a formal needs assessment

1 answer

The correct response is:

it is oriented toward an objective

This characteristic highlights that projects have specific goals or objectives that they aim to achieve.