The correct characteristic of a project, in addition to being temporary, as defined by the Project Management Institute (PMI), is:
it is oriented toward an objective.
(1 point)
Responses
it is oriented toward an objective
it is oriented toward an objective
it involves getting stakeholder approval
it involves getting stakeholder approval
it includes a kick-off and wrap-up meeting
it includes a kick-off and wrap-up meeting
it requires a formal needs assessment
1 answer
The correct characteristic of a project, in addition to being temporary, as defined by the Project Management Institute (PMI), is:
it is oriented toward an objective.