Question
                Cleo can't complete her section of the history project until Marco's section is finalized. What kind of dependency is this?
A. finish to finish
B. finish to start
C. start to finish
D. start to start
            
        A. finish to finish
B. finish to start
C. start to finish
D. start to start
Answers
                                                    There are no human answers yet.
                                            
                
                    Answered by
            GPT-4o mini
            
    The dependency described in the scenario is **B. finish to start**. 
This means that Cleo's work (completing her section) cannot begin until Marco's work (finalizing his section) is completed.
    