                Crew Size:  2 
Components, timing and sequencing - all times are in weeks:
Components Time to Deliver Assembly Time Assembly Sequence
Canopy 2 1 To fuselage after instruments
Spinner 1 1 To engine after propeller
Rudder 3 1 To fuselage after stabilizer
Undercarriage 5 1 To fuselage before engine
Fuselage 8 12 Anytime
Stabilizer 3 1 To fuselage after wings
Engine 12 5 To fuselage
Propeller 10 1 To engine
Instruments 9 6 To fuselage
Wings 8 16 To fuselage
Cowling
4 1 To fuselage after engine
  
Use the Activity on the Arrow technique to diagram this project.
Mark the critical path.
            
            
        Components, timing and sequencing - all times are in weeks:
Components Time to Deliver Assembly Time Assembly Sequence
Canopy 2 1 To fuselage after instruments
Spinner 1 1 To engine after propeller
Rudder 3 1 To fuselage after stabilizer
Undercarriage 5 1 To fuselage before engine
Fuselage 8 12 Anytime
Stabilizer 3 1 To fuselage after wings
Engine 12 5 To fuselage
Propeller 10 1 To engine
Instruments 9 6 To fuselage
Wings 8 16 To fuselage
Cowling
4 1 To fuselage after engine
Use the Activity on the Arrow technique to diagram this project.
Mark the critical path.
Answers
                    Answered by
            Ms. Sue
            
    How would you like us to help you?
If you don't want help, why did you post this here?
    
If you don't want help, why did you post this here?
                                                    There are no AI answers yet. The ability to request AI answers is coming soon!
                                            
                Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.