10men work dig 6h per day cording 60m in 14 days, how long will it take 7 men who work 10h per day to dig 30m
3 years ago

Answers

Answered by Anonymous
10 men / 7 men * 6 h / 10 h * 30 m / 60 m * 14 days =
3 years ago
There are no AI answers yet. The ability to request AI answers is coming soon!

Submit Your Answer


We prioritize human answers over AI answers.

If you are human, and you can answer this question, please submit your answer.

Related Questions

How much 60% concentrated cordial must be added to 90% concentrated cordial to make 6L of 80% cordia... which era was the western cordillera formed in(precambrian, paleozoic, mesozoic, or cenezoic)? WEEK 5 - Work Rates You work in retail. In the past you inventoried and shelved the weekly UPS shi... Work or no work? Work=ForcexDistance 1. A person holding a box of potatoes. No work 2. A batter... Does work work refer to the type of paid employment? Yes or no? Ok work... work = net force parallel to displacement lets say something was pushed up a ramp at... 9/1-7/11 with work thank you i dont understand how i get the mixed number 8 4/11 5-m=3 1/8 how do I work this problem out? Sal and Cal both work for the same company making ​$55,000 each in annual salary. Sal deposits 5​% o... 8w-11=45 Please work this out for me Thanks.
Submit Your Answer

Question

10men work dig 6h per day cording 60m in 14 days, how long will it take 7 men who work 10h per day to dig 30m

Ask a New Question
Archives Contact Us Privacy Policy Terms of Use