A can do a certain work in 30 days. B is 25% more efficient than A, and C is 20% more efficient than B. A and B work together for 10 days. C alone completes the remaining work in x days. the value of x is
Answers
Answered by
mathhelper
Assuming by "more efficient" you mean that he has a better rate.
Let the job to be done be 1 units of work
Let A's rate be 1/30
then B's rate is 1.25(1/30) = 1.25/30 = 1/24
C's rare is 1.2(1.25/30) = 1/20
combined rate of A and B = 1/30 + 1/24 = 3/40
working for 10 days, work done is 10(3/40) = 3/4
work remaining to be done = 1 - 3/4 = 1/3
time taken by C = x
x = (1/3) / (1/20) = 20/3 days or 6 2/3 days
Let the job to be done be 1 units of work
Let A's rate be 1/30
then B's rate is 1.25(1/30) = 1.25/30 = 1/24
C's rare is 1.2(1.25/30) = 1/20
combined rate of A and B = 1/30 + 1/24 = 3/40
working for 10 days, work done is 10(3/40) = 3/4
work remaining to be done = 1 - 3/4 = 1/3
time taken by C = x
x = (1/3) / (1/20) = 20/3 days or 6 2/3 days
Answered by
Kaur
It should be 1/4 รท 1/20 ??????
Answered by
mathhelper
Of course, it was a carry-over-typo
Sorry about that.
Sorry about that.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.