A Gantt Chart is good for planning but not an effective tool for control. Can you please let me know if it is true or false and why?

The answer is "true".

See "Advantages and limitations" at
http://en.wikipedia.org/wiki/Gantt_chart

It tends to give too rosy a picture of project status, and fails to show the importance and consequences of meeting or not meeting deadlines along critical paths.
18 years ago

Answers

Related Questions

I AM MAKING A GANTT CHART IN MS PROJECT.I CANNOT CHANGE THE START AND FINISHVDATE...IT IS SOMEHOW BL... Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a p... . Construct a Gantt chart and project network for the following set of activities, compute the lengt... A Gantt chart is good for planning but not an effective tool for control. . True False What is tracking Gantt chart 9. SJN Gantt Chart with Completion Times Draw a Gantt chart that shows the completion times for each process using first-come, first-served... Draw a Gantt chart that shows the completion times for each process using shortest job next CPU sch... Draw a Gantt chart that shows the completion times for each process using round robin CPU schedulin... 10. Round Robin Gantt chart with completion Times Time Slice = 60 P1 – Service time = P2 – Servic...
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use