A pulley system of 4 pulley has an efficincy of 70% what effort would be needed to lift a load of 300N with the aid of a machine
5 years ago

Answers

R_scott
effort = (load / number of pulleys) / efficiency ... (300 N / 4) / 70%
5 years ago

Related Questions

A pulley system os being used to raise a load. The rope begins at the ceilings, goes down, round a p... A pulley system having 5 pulleys is used to raise a 450N load. find the mechanical advatange and hen... In using a pulley system,an Effort of 100N is needed to raise steadly a load of 800N.(a)what is the... A pulley system with IMA of 4 requires a force of 15 New Ton tol lift a load of 45 New Ton. Find the... By using a pulley system, a farmer makes it easier to lift bales of hay by reducing the force needed... In using a pulley system, an effort of 100N is needed to raise steadily a load of 800N through a dis... A pulley system is only 25% efficient. What could make it more efficient?(1 point) Responses Increas... When using a pulley system, force (increases/decreases) and distance (increases/decreases). When using a pulley system, force (increases/decreases) and distance (increases/decreases).
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use