Asked by Matt
Calculate the following using excel (show all work):
Income statement and cash flow statement for Project
Smith Machine Company uses a MARR of 10% and depreciates its assets using a seven-year MACRS. Smith Machine Company’s effective income tax rate is 25%.
Data:
Equipment cost- $35,000 including trade in allowance and sales tax. The total cost of the shipping and handling is $7,500. The total cost to install the coolant system is $68,000. Setup cost of the coolant system will be $13,500. The useful life of the coolant system is 8 years. The coolant system are to be sold at the end of the project for $8,000
Each coolant system will require 1 operator at a rate of $24/hr. The Company shop operates 4080 hr/yr. The total maintenance labor cost is 20% of operating hours at $19/hr. Total annual direct materials are $275,000. Manufacturing overhead excluding depreciation is presumed to be an additional $165,00/yr.
Revenues are expected to be $625,000 for the first year as a result of the project and is expected to increase by 3% each year throughout the project. The project will run for 8 years
Income statement and cash flow statement for Project
Smith Machine Company uses a MARR of 10% and depreciates its assets using a seven-year MACRS. Smith Machine Company’s effective income tax rate is 25%.
Data:
Equipment cost- $35,000 including trade in allowance and sales tax. The total cost of the shipping and handling is $7,500. The total cost to install the coolant system is $68,000. Setup cost of the coolant system will be $13,500. The useful life of the coolant system is 8 years. The coolant system are to be sold at the end of the project for $8,000
Each coolant system will require 1 operator at a rate of $24/hr. The Company shop operates 4080 hr/yr. The total maintenance labor cost is 20% of operating hours at $19/hr. Total annual direct materials are $275,000. Manufacturing overhead excluding depreciation is presumed to be an additional $165,00/yr.
Revenues are expected to be $625,000 for the first year as a result of the project and is expected to increase by 3% each year throughout the project. The project will run for 8 years
Answers
There are no human answers yet.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.