3. A rectangular building measures 42′ in length and 24′ in width. The four exterior walls have a sill-to-top-plate distance of 9′. How many 4 × 8 sheets of plywood sheathing would be needed to cover the four exterior walls of this building? (Note: Round up the number of sheets needed to the next full sheet. Do not allow for waste.)
A. 35
B. 39
[C. 38]
D. 33
4. How many fascia boards would you need for a building that's 38′ × 50′? The roof overhang will be 2′.
[A. 12]
B. 10
C. 6
D. 11
5. A carpenter needs to calculate the correct length of the wall studs for a platform-frame construction. The building will have a finished floor-to-ceiling height of 7′8½″, a 1″-thick finish floor, ¾″ furring strips in the ceiling, and ½″ gypsum board on the ceiling. The combined thickness of the top plates and the sole plates is 4¾″. What would be the correct stud length for this building?
A. 7′7½″
[B. 7′9½″]
C. 7′8¾″
D. 7′6″
6. What is the length of wall studs when the finished floor-to-ceiling height is 8′, ceiling material is ¾″ thick, the finished floor is ¾″ thick, and it's framed with three plates?
A. 7′9″
[B. 8′1½″]
C. 8′
D. 7′7½″
7. A carpenter needs to calculate the correct length of the wall studs for a platform-frame construction. The building will have a finished floor-to-ceiling height of 8′, a ¾″-thick hardwood finish floor, ¾″ furring strips in the ceiling, and ½″ gypsum board on the ceiling. The combined thickness of the top plates and the sole plates is 4½″. What would be the correct stud length for this building?
A. 8′1″
B. 7′10½″
C. 7′8½″
[D. 7′9½″]
8. A carpenter needs to determine how many plywood subflooring panels will be needed for a particular job. The area that needs to be covered measures 24′ × 48′. How many 4 × 8 plywood subfloor panels would be needed to cover this area?
[A. 36]
B. 32
C. 40
D. 34
A. 35
B. 39
[C. 38]
D. 33
4. How many fascia boards would you need for a building that's 38′ × 50′? The roof overhang will be 2′.
[A. 12]
B. 10
C. 6
D. 11
5. A carpenter needs to calculate the correct length of the wall studs for a platform-frame construction. The building will have a finished floor-to-ceiling height of 7′8½″, a 1″-thick finish floor, ¾″ furring strips in the ceiling, and ½″ gypsum board on the ceiling. The combined thickness of the top plates and the sole plates is 4¾″. What would be the correct stud length for this building?
A. 7′7½″
[B. 7′9½″]
C. 7′8¾″
D. 7′6″
6. What is the length of wall studs when the finished floor-to-ceiling height is 8′, ceiling material is ¾″ thick, the finished floor is ¾″ thick, and it's framed with three plates?
A. 7′9″
[B. 8′1½″]
C. 8′
D. 7′7½″
7. A carpenter needs to calculate the correct length of the wall studs for a platform-frame construction. The building will have a finished floor-to-ceiling height of 8′, a ¾″-thick hardwood finish floor, ¾″ furring strips in the ceiling, and ½″ gypsum board on the ceiling. The combined thickness of the top plates and the sole plates is 4½″. What would be the correct stud length for this building?
A. 8′1″
B. 7′10½″
C. 7′8½″
[D. 7′9½″]
8. A carpenter needs to determine how many plywood subflooring panels will be needed for a particular job. The area that needs to be covered measures 24′ × 48′. How many 4 × 8 plywood subfloor panels would be needed to cover this area?
[A. 36]
B. 32
C. 40
D. 34
Answers
Answered by
doug
I redid number 7 and I believe that one to be A.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.