A engine for a car can be manufactured in a factory every 35 minutes. The factory starts production at 8:45 and stops at 16:55.
(i) Find the number of engines that can be produced in a single working day.
After a refit of the factory, an engine can be produced 4 minutes more quickly than before.
(ii) Find the number of completed engines that can now be produced in a single day?
I really need help with these questions!!! Please help!
(i) Find the number of engines that can be produced in a single working day.
After a refit of the factory, an engine can be produced 4 minutes more quickly than before.
(ii) Find the number of completed engines that can now be produced in a single day?
I really need help with these questions!!! Please help!
Answers
Answered by
Ms. Sue
Faith/Vanessa -- I wonder why I took the time and effort to answer most of this question below if you don't even bother responding to it.
https://www.jiskha.com/display.cgi?id=1504738727
https://www.jiskha.com/display.cgi?id=1504738727
Answered by
Steve
a work day has 15+60*7+55 = 485 minutes
(1) 485/35 = 13.8
(ii) 485/31 = 15.6
(1) 485/35 = 13.8
(ii) 485/31 = 15.6
Answered by
Steve
Oops. That's 490, as Ms. Sue said, but the answers stay the same.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.