Use z-scores.
Formula:
z = (x - mean)/sd
You are looking to solve for x, so fill in the rest of the formula with what you know.
Find z using z-table (problem gives you percentage). Mean = 80 and standard deviation = 10.
I hope this will help get you started.
1. The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the dues date of the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
4 answers
88.1594
the time requested to complete a project is normally distributed with a mean of 80 weeks and standard deviation of 10 weeks. the construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure if finishing by the due date, what due date (project week number) should be negotiated?
92.8