Your program has an RDT&E-funded project scheduled to start in July 2005 which is expected to take 12 months to complete. The p...Asked by Glennis
Your program has an RDT&E-funded project scheduled to start in January 2005 which is expected to take 16 months to complete. The project is expected to cost a total of $16 million (then-year dollars), with cost expected to be incurred at a rate of $1 million per month. The services to be provided under this project are NOT severable, and it has been determined that no contractor is willing to accept a contract for less than the entire 16 months of effort. What is the correct amount to include in your budget request for this project?
Answers
Answered by
Anonymous
$9 million for fY 15 and $ 7 million for fy16