Your program has an RDT&E-funded project scheduled to start in July 2005 which is expected to take 12 months to complete. The p...Asked by James
Your program has a proposed RDT&E-funded project scheduled to start in January 2005 which is expected to take 16 months to complete. The project is expected to cost a total of $16 million (then-year dollars), with cost expected to be incurred at a rate of $1 million per month. The work to be performed under this project is Non-Divisible effort. It also has been determined that no contractor is willing to accept a contract for less than the entire 16 months of effort. What is the correct amount to include in your budget request for this project?
$ 9 million for FY04 and $ 7 million for FY05
$ 9 million for FY05 and $ 7 million for FY06
$ 16 million for FY05 and $ 0 million for FY06
$ 16 million for FY04 and $ 0 million for FY05
$ 9 million for FY04 and $ 7 million for FY05
$ 9 million for FY05 and $ 7 million for FY06
$ 16 million for FY05 and $ 0 million for FY06
$ 16 million for FY04 and $ 0 million for FY05
Answers
There are no human answers yet.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.