You are a supervisor for a software development team. You see that your team has added the following phases to the calendar for a new project: planning, design, test, and maintenance. Which phases are missing, and what is their correct order?

Responses

development, implementation, requirements analysis

requirements analysis, implementation, development

requirements analysis, development, implementation

implementation, requirements analysis, development

1 answer

The correct order and the missing phases are:

- requirements analysis
- design
- development
- implementation
- test
- maintenance

So the missing phases are design and implementation. The correct order would be:

requirements analysis, design, development, implementation, test, maintenance.