The correct order of the phases is: requirements analysis, development, implementation.
So the missing phases are development and implementation.
You are a supervisor for a software development team. You see that your team has added the following phases to the calendar for a new project: planning, design, test, and maintenance. Which phases are missing, and what is their correct order?
(1 point)
Responses
development, implementation, requirements analysis
development, implementation, requirements analysis
requirements analysis, implementation, development
requirements analysis, implementation, development
requirements analysis, development, implementation
requirements analysis, development, implementation
implementation, requirements analysis, development
1 answer