The correct statement is:
Activities on the critical path take the shortest time to be completed.
Which statement is true of Critical Path Method (CPM)?
Question 4 options:
Activities on the critical path take the shortest time to be completed.
It determines the critical path for the completion of a series of interrelated activities.
Activities that are on the critical path are flexible and can be delayed without delaying a project.
A delay in the activities of a project does not affect the scheduled delivery of the project.
1 answer