The correct answer is: to identify potential problems that could impact the schedule.
Tracking the progress of a plan helps identify any potential problems or delays that could impact the schedule. This allows for proactive measures to be taken to address these issues and ensure the plan stays on track. Providing information for managers reports and creating a progress chart for employees may be additional benefits of tracking progress, but the main reason is to identify potential problems. Checking whether the plan is based on faulty assumptions is typically done during the planning phase rather than tracking progress.
Which of the followingexmplains why is is necesary to track the progress of a plan
to provide information for managers reports
to ensure the plan is based on faulty assumptions
to create a progress chart for employees to help them calculate their pay
to identify potential problems that could impact the schedule