a) Increased upfront capital costs
b) Lower operating costs
c) Higher interest rates
d) Longer project lifetime
e) Increased capacity factor
b) Lower operating costs
d) Longer project lifetime
e) Increased capacity factor
Which of the following would lower the levelized cost of energy (LCOE) for a project? Select all that
1 answer