What are some examples of situations encountered by Projects within your Company that would greatly benefit from contingency planning?

Many, many high value ship overhaul projects where repair parts are in the critical path schedule. Often, it is cheaper to have two parallel sources for parts, and even having one made to relieve schedule costs.