Asked by Anonymous
                We are going to build a PV system on a roof of 10m2, and we have two possible PV modules:
(1) A first generation module with efficiency η=17% and cost of 0.80€/Wp.
(2) A second generation PV module with efficiency η=10% and cost of 0.40€/Wp.
The non-modular costs are 100€/m2.
Assume that the rooftop enjoys an irradiance of 1000W/m2.
1. What is the cost in € of implementing a PV system for the entire roof using first generation technologies?
2. What is the cost in € of implementing a PV system for the entire roof using second generation technologies?
3. If the power demand is 700Wp, which will be the most cost effective option? (Note that for meeting the power demand, you may not need the whole roof area.)
            
        (1) A first generation module with efficiency η=17% and cost of 0.80€/Wp.
(2) A second generation PV module with efficiency η=10% and cost of 0.40€/Wp.
The non-modular costs are 100€/m2.
Assume that the rooftop enjoys an irradiance of 1000W/m2.
1. What is the cost in € of implementing a PV system for the entire roof using first generation technologies?
2. What is the cost in € of implementing a PV system for the entire roof using second generation technologies?
3. If the power demand is 700Wp, which will be the most cost effective option? (Note that for meeting the power demand, you may not need the whole roof area.)
Answers
                    Answered by
            fari
            
    plz help me whats the solution of this question.
    
                    Answered by
            BOb
            
    For Question 1: 2440 
Total PV output = 1000W/m2×18%×10m2=1800W
PV module costs = 1800W×€0.8/Wp=€1440.
Non-modular costs = €100/m2×10m2=€1000.
Total cost = PV module costs + non-modular costs = €2440.
    
Total PV output = 1000W/m2×18%×10m2=1800W
PV module costs = 1800W×€0.8/Wp=€1440.
Non-modular costs = €100/m2×10m2=€1000.
Total cost = PV module costs + non-modular costs = €2440.
                    Answered by
            fvr
            
    2440
    
                    Answered by
            jhv
            
    ggkbh
    
                    Answered by
            Anonymous
            
    does anyone know the answer to the 3rd part?
    
                    Answered by
            Fan of Solar Energy
            
    AQ1.1.1 Costs of PV Technology Generations
(Note: due to requests from many students, to clarify the exercise and enhance the differences between the two options, the efficiency of the first generation module was changed from 17% to 18%. The correct answer to AQ1.1.3 remains the same as before).
We are going to build a PV system on a roof of 10m2, and we have two possible PV modules:
(1) A first generation module with efficiency η=18% and cost of
€0.80€/Wp.
(2) A second generation PV module with efficiency η=10% and cost of
€0.40€/Wp.
The non-modular costs are
€100€/m2.
Note that the irradiance under standard test conditions is 1000W/m2.
What is the cost in € of implementing a PV system for the entire roof using first generation technologies?
Explanation Irradiance = 1000W/m2.
PV area = 10m2.
Module efficiency η=18%
Total PV output = 1000W/m2×18%×10m2=1800W
PV module costs = €1800W×€0.8/Wp=€1440.
Non-modular costs = €100/m2×10m2=€1000.
Total cost = PV module costs + non-modular costs = €2440.
AQ1.1.2 Costs of PV Technology Generations
What is the cost in € of implementing a PV system for the entire roof using second generation technologies?
Explanation Irradiance = 1000W/m2.
PV area = 10m2.
Module efficiency η=10%
Total PV output = 1000W/m2×10%×10m2=1000W
PV module costs = €1000W×€0.4/Wp=€400.
Non-modular costs = €100/m2×10m2=€1000.
Total cost = PV module costs + non-modular costs = €1400.
    
(Note: due to requests from many students, to clarify the exercise and enhance the differences between the two options, the efficiency of the first generation module was changed from 17% to 18%. The correct answer to AQ1.1.3 remains the same as before).
We are going to build a PV system on a roof of 10m2, and we have two possible PV modules:
(1) A first generation module with efficiency η=18% and cost of
€0.80€/Wp.
(2) A second generation PV module with efficiency η=10% and cost of
€0.40€/Wp.
The non-modular costs are
€100€/m2.
Note that the irradiance under standard test conditions is 1000W/m2.
What is the cost in € of implementing a PV system for the entire roof using first generation technologies?
Explanation Irradiance = 1000W/m2.
PV area = 10m2.
Module efficiency η=18%
Total PV output = 1000W/m2×18%×10m2=1800W
PV module costs = €1800W×€0.8/Wp=€1440.
Non-modular costs = €100/m2×10m2=€1000.
Total cost = PV module costs + non-modular costs = €2440.
AQ1.1.2 Costs of PV Technology Generations
What is the cost in € of implementing a PV system for the entire roof using second generation technologies?
Explanation Irradiance = 1000W/m2.
PV area = 10m2.
Module efficiency η=10%
Total PV output = 1000W/m2×10%×10m2=1000W
PV module costs = €1000W×€0.4/Wp=€400.
Non-modular costs = €100/m2×10m2=€1000.
Total cost = PV module costs + non-modular costs = €1400.
                    Answered by
            vergas
            
    Q3 is first generation
    
                    Answered by
            Anonymous
            
    1.1.1
Ans:2440
1.1.2
Ans:1440
1.1.3
Ans:first generation technology
    
Ans:2440
1.1.2
Ans:1440
1.1.3
Ans:first generation technology
                    Answered by
            MATHEVAN
            
    VERYNICE AND VERY MUCH USEFUL
    
                    Answered by
            MATHEVAN
            
    The worldwide installed wind power in 2012 was  280GW . Assume that the total electricity generation worldwide is  20200TWh  per year, and a capacity factor for wind power of  30% .
What percentage of the total electricity generation worldwide was covered by wind energy in 2012?
    
What percentage of the total electricity generation worldwide was covered by wind energy in 2012?
                    Answered by
            Vamsi sannidhi
            
    3.642%
    
                                                    There are no AI answers yet. The ability to request AI answers is coming soon!
                                            
                Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.