Warnock Inc is considering a project that has the following cash flow and WACC Data What is the projects NPV ?note THAT a projects NPV Can be negative in which case it will be rejected .

WACC 10.00%
year 0 1 2 3
Cash Flows -825 500 400 300

I get C but i am having doubts about my answer can you help me.

2 answers

I do not know what answer C represents, but you could work out according to the example given in
http://www.jiskha.com/display.cgi?id=1248867678
and make the correct choice.
I got 60.52 as well. I added up all of the present values.