Uma is project managing a website development project. Once she has developed a schedule, which step will she MOST likely perform next?

(1 point)
Responses

create a list of milestones

create a list of milestones

assign tasks to team members

assign tasks to team members

make a quality-control plan

make a quality-control plan

scope the project size and timeline

1 answer

After developing a schedule for a website development project, Uma will most likely perform the next step of assigning tasks to team members. This step is crucial for ensuring that work is distributed according to the schedule and that team members know their responsibilities.