Orginal Budget Budgeted Volume Budgeted Quantity Budgeted Price

1,000 40.00 $40,000.00 F
Flexible Budget Actual Value Budgeted Quantity Budgeted Price
1,200 41.67 $50,000.00 UF


Orginal Budget/Flexible Budget Budgeted Volume Budgeted Quantity Budgeted Price
1,000 $40.00 $40,000
Actual Value Budgeted Quantity Budgeted Price
1,200 $41.67 $50,004 UF



Problem:Project Budget was for 1,000 hours of part-time nurses services at $40.00 per hour, for
a total cost of $40,000. It was expected that these nurses' woruld treat 2,000 patients. After
the flu season was over, it turned out that the total spent on part-time nurses' was $50,000.
The nurses' worked 1,200 hours and 2,600 patients were treated. Calculate the varriances.
Was the overall result favorable or unfavorable?

1 answer

Favorable
Similar Questions
  1. Orginal Budget Budgeted Volume Budgeted Quantity Budgeted Price1,000 40.00 $40,000.00 F Flexible Budget Actual Value Budgeted
    1. answers icon 0 answers
  2. Current Attempt in ProgressIn the Bramble Corp., indirect labor is budgeted for $101250 and factory supervision is budgeted for
    1. answers icon 3 answers
    1. answers icon 1 answer
  3. The federal budget passed by Congressand signed by the president shows the relationship between budgeted expenditures and
    1. answers icon 2 answers
more similar questions