Last month, the release of information specialist received 232 requests for information. He was able to answer 176 within the specified time frame of three working days. What is the rate of compliance in answering requests within the specified time frame?

3 answers

100(176 * 232) = ______%
Dear Sue,
Do you mean (176/232)100 = 75.86%
Thank you
Oops! I goofed!

Yes. You're right.