Jamaal is initiating a new design project. Once he has identified all the tasks necessary to complete for the project, which step will he MOST likely perform next?

(1 point)
Responses

develop a quality checklist

develop a quality checklist

assign team members to tasks

assign team members to tasks

train team members as needed

train team members as needed

hold a project kick-off meeting

1 answer

After identifying all the tasks necessary to complete the design project, Jamaal will MOST likely perform the next step of assigning team members to tasks. This step is critical for ensuring that each task has a designated responsible person and that the project can move forward effectively.